The Architect-Engineer Design and Build
Process |
|
Introduction Details
of JRL's Design Build Process. Read the detail or skip to the sections of
interest using one of these links. The AE Role --
Starting the Process -- The Design
Program -- Design (Preliminary, Concept, Working
Drawing) -- Construction Documentation --
Construction Management -- Bids -- Approvals --
Construction Review -- CloseOut
-- Warranty Period -- Selecting an Architect-Engineer--
AEs to Avoid -- Fees
-- Specialty Research -- Manufacturing & Industry
Do you need an
Architect-Engineer?
Laws vary by region, but
generally an architect or engineer or both are required to perform the design
and review of construction for new buildings, renovations or additions with a
floor area of over 6,000 square feet. The exception to this is the building
type known as Assembly Buildings, such as schools, community centres,
theatres, libraries, swimming pools, etc., where the services of an
architect-engineer are required regardless of the floor area of the proposed
construction. Commercial construction usually involves and Architect-Engineer
[A/E] team
Most people don't realize how
complicated it can be to build or renovate - until they have to deal with
building codes, zoning laws, hiring contractors and making sure that the work
is done properly. There is never any single, clear-cut path through this maze,
because no two projects are exactly alike. This is where the A/E, drawing on
their extensive training and experience, can provide invaluable assistance in
the process. In most cases, the cost of hiring an A/E can be returned many
times over by savings reaped from an efficient design, properly specified
materials, thoroughly prepared construction documents, assistance with the
selection of a contractor and review during the construction phase. JRL offers
a complete complement of project development and engineering services from site
selection to completed completed construction and occupancy or
startup. |
|
| The
Architect-Engineer's Role
As a part of his services,
the A/E will discuss your goals, requirements, budget, and special needs. He
will visit and study your site. The A/E will then work to translate your dreams
into reality in the form of design concept sketches. Next, he will prepare a
detailed set of construction drawings and specifications. These construction
documents will be used to obtain accurate and comparable bids. The A/E will
help you select appropriate contractors to bid your project, review those bids
and assist in selecting your builder.
The A/E will also provide
assistance throughout the construction of the Project. He will observe the
construction process, help with changes, look out for quality control, assist
in making design decisions and professionally represent the owner's interests.
|
|
| STARTING THE PROCESS:
The first step in your
construction is the selection and purchase of the land. Most clients own their
property before finding an architectural engineering firm, but for those who do
not, the A/E's advice prior to purchase is strongly recommended. Your A/E can
visit available properties, evaluate those best suited to client needs and
goals, study the property and look for any potential problems that might make
construction more difficult or expensive. Once the land is purchased a number
of studies are needed before design can start; a site survey showing contours,
boundaries, setbacks, trees and rocks; a soil test outlining foundation,
drainage, and septic requirements. The A/E can provide names of qualified
surveyors and soil engineers or they may coordinate the necessary studies in
your behalf. A review of design covenants, codes or legal restrictions applying
to the land are also important. Depending on the size of the structure and
conditions such as expansive soils or seismic zone, other studies may be needed
for engineered foundation plans and structural considerations.
THE
PROGRAM:
Next the owners and the A/E
will develop a written description or program, that lists the requirements for
the project. This is a detailed list of rooms and room sizes, how the spaces
will relate to one another, lighting, access and aesthetic considerations. If
our client has special requirements such as solar heat this is the time the A/E
will discuss it. Clients often bring a file containing notes, photos and
magazine clippings or tenant requirements to give the architect a better idea
of their intentions and desires. From this program, the A/E will estimate the
size of the proposed structure. Based on various factors & recent similar
jobs, the A/E will prepare an estimated cost for the project. If this proposed
cost is not within the budget, the program is then revised, with reductions in
size or quality or an increase in budget before the project proceeds into the
design phase.
A/E's specialise in creative
problem solving. The process begins by determining your needs and budget. By
considering variables such as site constraints, building codes, local climatic
conditions, energy efficiency, functional requirements and the latest
technology in construction materials and methods, the A/E team will provide
alternatives to meet your particular requirements. The A-E plans your project
with you. As your ideas evolve, changes can be made on paper rather than during
construction. By thoroughly exploring available solutions to your needs at this
stage, costly changes during construction can be avoided. |
| Design (Preliminary, Concept, Working
Drawing)
Based on the Design site
analysis and program, the A/E begins work on a design. For large projects, the
design may be broken into phases to provide milestones for both the A/E and the
client. The A/E will prepare sketchs of site plans showing structure location
and driveway access, plans showing room layouts and sizes, and elevations
showing a rough concept for the exterior of the structure. During this phase
the A/E takes factual, objective information, solves the practical problems and
arrives at a subjective solution in the form of an attractive design. Owners
review design concept sketches, concentrating on the overall concept. Small
details come into consideration later. Design concepts are revised and refined
based on the owner's' feedback.
Once the Concept is
established, Final design drawings are drawn at a larger scale and
incorporating structural and mechanical considerations. These are the owner's
final review of the design prior to starting the construction drawings. To help
you visualize the design, the A/E may produce three dimensional drawings,
commonly known as "perspectives" or "renderings". Depending on the type and
complexity of the project, the A/E will produce simple models illustrating the
basic features of the design. If more detailed models are required, these can
be provided, normally at an additional cost. |
|
| Construction Documentation
Once the design has been
finalized, production of construction documents (commonly called "contract
documents") begins. After the owner has approved the final design drawings, the
architect begins the construction documents. A typical set of construction
drawings includes a site plan, foundation plan, floor plans, exterior
elevations, building sections, details, framing and roof plans, and interior
elevations. Mechanical and electrical layout sheets are drawn. Various
mechanical and electrical Schedules will be prepared including such items as
heat loss and energy calculations. The A/E will produce a detailed set of
drawings illustrating the construction materials and assemblies required to
execute the approved design. Depending on the scope of the project, other
consultants may be involved, such as structural engineers,
mechanical/electrical engineers, or landscape architects. The architect directs
and co-ordinates the work of these other consultants. Specifications will be
produced setting out all required materials, quality and construction methods
and workmanship.
There are three main uses for
the construction documents. Detailed drawings and specifications allow for
accurate, comparable bids from contractors. The documents will be reviewed by
the building department before issuing permits. And, of course, the drawings
and specifications will be used by the contractor and sub-contractors to
execute the construction. |
|
| Bids
Some owners will have already
selected their contractor prior to designing the structure. In this case, the
contractor often will participate in the design process, providing preliminary
cost estimates and conferring with the architect on details and specifications.
At this stage the contractor would do a detailed cost breakdown and prepare a
contract, and the owner would then proceed with financing. In other cases, a
client will have several contractors bid the project. The winning contractor
will be selected because of price, reputation, and compatibility with the
owner.
The final drawings and
specifications will form the basis of bids tendered by contractors. Depending
on the type and scope of the project, bids can be solicited from contractors by
open tender, invited tender, or negotiated with a contractor pre-selected by
you.
Once bids are received, the
A/E will review the bids and assist you in selecting the contractor. The A/E
will draw up the construction contract and preside over the signing of the
contract and receipt of items such as proof of the contractor's liability
insurance, financial stability, etc. |
|
| Approvals
Concurrent with the bid
process, the A/E may persue the various permit approvals required before
construction can begin. This may include demolition permits, site plan
approval, zoning approval, and finally, the building permit. Often times the
approvals are a part of the construction contract. The goal is to have all
approval in place at or immediately after the signing of the construction
contract, so that construction can begin immediately. Any delays at this stage
can have a financial impact on the project, since the contractor would be
within his right to request additional compensation if construction is delayed
beyond a reasonable period after the signing of the contract. The A/E will
obtain permits and monitor the permits furnished by the contractor to keep the
project moving smoothly. |
|
| Construction Review
With a signed contract and
all approvals in place, construction begins. During construction the A/E makes
periodic visits to the job site. His role is to observe the work, to see that
the project is being built as designed and to help resolve any problems or make
changes requested by the owner. The A/E will monitor construction progress, and
review the work to ensure that it conforms to the requirements of the drawings
and specifications. The A/E will review and certify payment requests from the
contractor. The A/E will produce site review reports and record deficiencies
requiring correction. Once construction is completed, the A/E will conduct a
final review, produce a deficiency list (usually referred to as the "Punch
List"). On large projects final reviews may be by floor or by some other
pre-determined phase. At the completion of the project, the owner, architect
and contractor take a final walk through to compile a punch list of any
remaining work requiring completion or repair. During the construction process
the architect acts as the owner's professional representative. and provide a
letter to the municipal building department certifying that the construction
was carried out in conformance with the construction documents and in
compliance with governing building codes. The latter is normally required by
municipalities in order to issue an "occupancy permit" which legally allows you
to occupy the new premises |
|
| Contract Close-Out
With the premises occupied,
the A/E's remaining tasks consist of following up with the contractor to ensure
that all deficiencies have been corrected, processing and approving final
payment, and ensuring that all required warranties are obtained on your behalf.
Once these are done, the contract is termed "closed-out" and the project is
officially completed. |
|
| Warranty Period
The A/E will act as a
resource to you during the warranty period, to assist in obtaining swift
corrective action from the contractor for any problems or deficiencies which
develop. The A/E can draw on his knowledge and experience to ensure that
problems due to faulty workmanship and materials which may occur during the
warranty period are properly recognized and responsibility for their correction
is accepted by the contractor.
The above summary is
representative of the basic process involved in the design and construction of
most projects, but should not be considered definitive. As every project is
unique, so are the steps required to bring it to a successful conclusion. The
A/E draws upon his experience and talents, and those of his staff and other
consultants, to plan and orchestrate the many tasks required to turn your
vision into reality. |
|
JRL also has a Research Consultants Servicewhich can
conduct energy, abatement, fire safety assessments, feasibility studies,
environmental reports and other developmental planning or upkeep and equipment
maintenance management decisions. And, Get information about AE Fees. If you have an industrial or